The land and water plan has been developed to align with current national direction and the regional policy statements. Below are some questions that you might have if you hold existing resource consents, operate under permitted activity rules in the current plans and/or are planning to undertake new activities that might affect land and water. If you have any other questions, please email:  policy@orc.govt.nz and we will get back to you directly. 

Will there be permitted activity rules in the pLWRP?

Under the RMA, there are a number of activities (related to the beds of lakes and rivers, water and discharges) that need to be permitted by a national environmental standard, a rule in a regional plan or a resource consent so that you can do them. This means that these activities must have a permitted activity rule or consenting framework available in a regional plan. 

This is different to activities on land, where if a plan does not mention the activity, it is permitted and there does not need to be a permitted activity rule in a plan. 

The land and water plan has many permitted activity rules to ensure low scale, low effects activities do not need to obtain consents. 

How do the governments proposed changes affect consent requirements?

How do Freshwater Farm Plans interact with the pLWRP?

The rollout of Freshwater Farms Plan in Otago is currently paused. Central Government has indicated that Freshwater Farm Plans will remain but that changes to the system will be made. The details of these changes have not yet been released. Council will adjust to these future changes once they become clear. Council staff will continue to be across changes made by Central Government and will update resources and documents to meet any new or amended legislation, as required. 

The use of farm plans as a pathway for a number of farming activities is being considered in the pLWRP. This means that the activities will be able to be managed through the farm plan instead of applying for a consent. 

My water take/discharge permit expires in 2025. Should I apply to replace it before the pLWRP is notified?

There are no restrictions on when you can apply to replace a consent. If you are applying to replace a consent for substantially the same activity, we recommend that you apply at least 6 months before your consent expires. This will allow you to keep operating under your current consent while your application for a replacement consent is being processed by Council. Note: If you do not apply for a replacement consent 6 months before your consent expires there is no guarantee that you can use your current consent once it expires, if a decision on your new application has not been made. 

For further information on this refer to: Exercising your consent after it expires - Practice note 

For example: if your consent expires in April 2025, it is recommended that you have an application lodged and formally accepted by Council before September 2024. 

The below are worth considering when deciding whether you lodge a ‘replacement’ application before or after notification of the pLWRP: 

The timing of when an application is lodged and what stage the new plan is in the plan making process will impact on what rules, objectives and policies need to be considered for a consent application. We appreciate this can be confusing. The below table provides an indication of what must be considered at different stages in the plan process for regional plans.

What rules do I need to consider for my current permitted activities and consented activities once the pLWRP is notified.

Table 2 below provides advice on what rule would generally apply between the pLWRP being notified and the rules in the pLWRP becoming operative Questions 6 to 9 are specific scenarios with further details[11]. What is an existing use rights activity is explained in Question 6 below. For specific advice about your situation please contact consent.enquries@orc.govt.nz. 

For further information on this refer to: Consenting under proposed and operative plans

When do I need to get consent for farming activities that are currently permitted but may require it under the pLWRP?

You will only need to apply for consents that may be required after the new rules are finalized (operative). From when the rules are finalised, you will have 6 months to either obtain consent, amend your activity to meet the permitted activity standards, have a farm plan in place (if the pathway is there for that activity) or stop the activity. 

The RMA provide for activities to continue to operate under existing use rights while the new land and water plan is being considered. These existing use rights apply when: 

  • you have lawfully established[12] an activity and you have not stopped the activity for more than 6 months since the plan was notified[13] (e.g. you have an existing offal pit or farm landfill that you use); 

  • the effects of the activity are the same or similar in scale, character and intensity from when the plan has been notified (e.g. where and what you discharge); and 

  • the activity needs a consent to operate under the pLWRP. 

It is likely that the land and water plan will not be operative until 2026 or beyond.  To support you in applying for consent, when it is time to do so, Council will prepare application forms, guidance materials and hold workshops. 

[12] Lawfully established means that when the activity commenced it was compliant with all the relevant planning rules and regulations at that point in time e.g. it met any permitted activity rules that applied. 

[13] The nature of the activity and when it is typically undertaken will be taken into consideration for this requirement. For a seasonal activity (e.g. Intensive Winter Grazing), the normal year round operation will be the basis for whether the activity has stopped or not. 

 

Table 3 provides a checklist for to determine if you have existing use rights.

Table 3: Checklist for existing use rights

Is the activity lawfully established

 

Has the activity been occurring since notification of the land and water plan with no breaks longer than 6 months

 

Is the activity the same as before notification of the land and water plan

 

Is the activity currently permitted or no consent is required

 

Is consent required under the land and water plan

 

 

I currently take water as a permitted activity. If the pLWRP makes this a consented activity, when do I need to get a consent by?

Refer to the checklist above. This approach applies to all permitted activities that would become consented under the land and water plan.  

If your current take was lawfully established (which means that when the take commenced it was compliant with all the relevant planning rules and regulations at that point in time), water is continued to be taken (with no breaks longer than 6 months) and there is no change to the maximum rates and volumes of water taken and what the water is used for, then you can continue to operate under the permitted activity rule in the Regional Plan: Water until the land and water plan is operative. 

Once the pLWRP is operative, you must apply for a consent within 6 months, amend your activity to meet the permitted activity rule or stop the activity. If you lodge a consent application, you can then continue to operate under the permitted activity rule in the Regional Plan: Water until your consent application is granted. 

Which rules will I follow to extract gravel, construct culverts or undertake works?

I can currently extract gravel, construct culverts and undertake works in the bed on my property under permitted activity rules. If the conditions on the permitted activity rules change under the pLWRP which rules do I have to follow when the pLWRP is notified?

If you can currently undertake these activities using the permitted activity rules of the RPW or RP:Waste and if the pLWRP also makes your activity permitted, once the land and water plan is notified you will need to consider both plans’ permitted activity rules. You will need to make sure you are meeting all parts/conditions of each permitted activity rule in order for the activity to be permitted.  

If you cannot meet the new permitted activity rule in the land and water plan, you will need to apply for a consent within 6 months of the rule becoming operative (see 6 and 7 above) or change the way you undertake your activity to meet the permitted activity conditions.  

Note: You need to consider both the current and proposed permitted activity rules and meet both rules to be permitted. This is until the new permitted activity rule is finalised. 

[1] related to the beds of lakes and rivers, water and discharges

[2] For further information on this refer to: Exercising your consent after it expires - Practice note

[3] For further information on this refer to: Exercising your consent after it expires - Practice note

[4] Copies of the oRPS and pRPS can be found here: Otago Regional Policy Statements (orc.govt.nz)

[5] For further information on this refer to: Consenting under proposed and operative plans

[6] RPW is Regional Plan: Water for Otago: Regional plan - Water (orc.govt.nz)

[7] RP:Waste is Regional Plan: Waste for Otago: Regional plan - Waste (orc.govt.nz)

[8] Key elements from case law: (1) the extent to which the proposed measure has been exposed to independent decision making (2) possible injustice to the applicant (3) the extent to which a new measure may represent a significant policy shift when compared to the provisions of the operative plan, or implement a coherent pattern of objectives and policies in a plan (4) Where there has been a significant shift in Council policy, and any new provisions accord with Part II of the RMA or the requirements of a national policy statement – then the objectives and policies in the proposed plan change may potentially be given more weight

[9] E.g. if in the RPW the activity is restricted discretionary activity but in the pLWRP the activity is discretionary, the activity will be processed as a discretionary activity.

[11] For further information on this refer to: Consenting under proposed and operative plans

[12] Lawfully established means that when the activity commenced it was compliant with all the relevant planning rules and regulations at that point in time e.g. it met any permitted activity rules that applied.

[13] The nature of the activity and when it is typically undertaken will be taken into consideration for this requirement. For a seasonal activity (e.g. Intensive Winter Grazing), the normal year round operation will be the basis for whether the activity has stopped or not.

[14] More information on when the RPW applies can be found here: National Environmental Standards for Plantation Forestry (NES-PF) (orc.govt.nz)