The Building Act 2004 introduced legislation for managing the safety of existing and new dams in New Zealand.
Under this act, regional councils must have a policy on how they will deal with dangerous dams, earthquake-prone dams and flood-prone dams in their region, and how the policy will apply to heritage dams.
This policy will generally only impact you if you have a classifiable dam that either you or your recognised engineer believes to be dangerous, earthquake-prone or flood-prone.
A dam is classifiable if:
Many small farm dams and ponds will be excluded from the regulations as they are unlikely to exceed the height and volume thresholds above.
Section 153 of the Building Act 2004 provides that a dam is ‘dangerous’ if it:
(a) is a dam classified as having a potential impact classification of medium or high; and
(b) is likely to fail -
Section 153A of the Building Act 2004 includes the definitions for a ‘earthquake-prone’ or ‘flood-prone’ dam.
A dam is an earthquake-prone dam if the dam—
(a) is a high potential impact dam or a medium potential impact dam; and
(b) is likely to fail in an earthquake threshold event (as defined in the regulations).
A dam is a flood-prone dam if the dam—
(a) is a high potential impact dam or a medium potential impact dam; and
(b) is likely to fail in a flood threshold event (as defined in the regulations).
Section 153 and 153A of the Building Act 2004 can be accessed at: https://www.legislation.govt.nz/act/public/2004/0072/latest/DLM307337.html
The definitions of a ‘moderate earthquake’, a ‘earthquake threshold event’, a ‘moderate flood’ and a ‘flood threshold event’ are provided in regulation 19 of the Building (Dam Safety) Regulations 2022
The policy must be read alongside the regulations which defines terms used in the Building Act in relation to dangerous, earthquake-prone and flood-prone dams.
The policy does not impact on your obligations under the regulations as a dam owner.
The policy sets out the ORC’s approach and priorities it will take in performing its functions in relation to dangerous, earthquake-prone and flood-prone dams in the Otago region.
For more information on the Dam Safety Regulations please find helpful resources here:
https://www.building.govt.nz/managing-buildings/dam-safety/resources
Council has always had a policy on dangerous, earthquake prone and flood prone dams. Dam owners will continue to have the primary responsibility for identifying, monitoring, reviewing and reporting on dangerous, earthquake-prone and flood-prone dams and for reducing or removing the risk of harm to people, property and the environment.
The Building Act requires dam owners (with medium or high potential impact classification) to immediately notify the ORC if they have reasonable grounds to believe their dam is dangerous.
The Act (and Policy) places obligations on a recognised engineer (engaged by the owner to provide a certificate for the purposes of sections 135(1)(b), 142(1)(b) or 150(2)(f) of the Act) to notify the ORC and the dam owner if he or she believes that the dam is dangerous. This must be done within 5 working days after the engineer forms their belief.
Unless the circumstances dictate otherwise, the ORC will seek to discuss options for action with the dam owner, with a view to obtaining from the owner a mutually acceptable proposal for reducing or removing the danger:
The regulations came into force on 13 May 2024.
You can email any questions on the draft Policy on Dangerous Dams, Earthquake-Prone and Flood-Prone Dams 2023 to damsafety@orc.govt.nz.
There is a useful resource already produced by the Ministry of Business, Innovation and Employment (MBIE) providing guidance on dam safety:
MBIE Dam Safety Guidance document "Guide to complying with the Dam Safety Regulations" on building.govt.nz
A copy of the Building Act 2004 can be found here: https://www.legislation.govt.nz/act/public/2004/0072/latest/DLM306036.html
Each regional council has its own policy on dangerous dams.
Guidance on the safe operation of dams, as published by the New Zealand Society on Large Dams
A dam's safety is dependent on its design and construction, how it is operated, and how its maintained.
New dam safety regulations came into effect May 2024. The ORC compliance team is here to help dam owners meet these regulations.